RV 14A QB Lead Times

I could not find any current posts on this so here is my question.


July 18, 2022 I ordered Empennage, QB Fuse, QB Wing, and Finish Kit.

I have recieved the Empennage (Jan 2023), and show the current status below on the remaining items:

QB Wing:Being Assembled: Crating 08/28/23 to 2/27/2024
QB Fuse:Being Assembled: Crating 10/8/2023 to 1/20/2024
Finish Kit:part Being Produced: Crating 11/6/2023 to 11/21/2023

I am not sure how the current laser cut part issue will effect these, but I doubt it will have a positve affect. Has anyone recently received any kits above, and if so, what date did they order? At this point, I am considering changing and building the Sling TSI.
 