I've had hardly anytime to work on the plane the last week mostly because I was blocked by not having enough double sided tape. Got the elevator's trailing edges taped in, foam ribs sealed in and the edges riveted.

On the wing side I've completed all of the large parts inventory. I'm half way through the ball of fasteners and bags. I've checked off all of the bags measured by weight and gone through all of the bags that require counting of parts that contain only one part (like bags of pop rivets). Basically I've gotten all the low hanging fruit and have only the bags containing random parts and bags of multi sized screws and endless nut plates.

Here it is in action:
https://youtu.be/PQe7DmQ9YM8
https://youtu.be/xFtbyS2e8ic

- KIlroy
__________________
-------------------
Dues paid (2017)
RV-14 #140394
Empennage - WIP
Wings - Inventory
YouTube Build Channel
Reply With Quote
  #42  
Old 09-02-2017, 07:59 AM
Mikeandmaz Mikeandmaz is offline
 
Join Date: Sep 2015
Location: England
Posts: 9
Default

Hi Kiljoy, PM sent
Reply With Quote
  #43  
Old 09-06-2017, 11:33 PM
kiljoy's Avatar
kiljoy kiljoy is offline
 
Join Date: Sep 2014
Location: San Francisco
Posts: 51
Default Because my life isn't complex enough

Hi all,

So I've polished off most of the elevators. The leading edges are done. I learned from my rudder experience and these went down very smoothly. I only accidentally put the lower skins on top of the upper skins on only one section of one elevator. Thankfully that was caught before riveting.

Anyways I've moved onto the wings. Inventory is done which is always fun. I've started on the ailerons first. I'll be doing those and the flaps first since they're small and I can hide them away. I'm basically doing all of the smaller work first. I may even do the tanks before the main wings? Not sure yet.

One thing I do know is that I bought crappy drill bits and trying to drill holes through that stainless steel counterweight bar has ruined about 3 drill bits so far.

On a side note my available building time I'm afraid is going to possibly be going down. The maintenance officer on the board of my flying club has retired. I was approached for the position and I've been elected to do the job. Now on top of my plane I'm responsible for maintaining a fleet of 4 aircraft and the 130 member's lives that fly them. It's a crash course to be sure but I'm leaning a lot. Just hired a great A&P to be the club's mechanic and I'm learning everything I've ever wanted to know.

Anyways, here are some videos from working on the wing. Enjoy:

https://youtu.be/40I_mF8KRF8
https://youtu.be/oTdtstz9zos
https://youtu.be/xmULgWlxM4M
https://youtu.be/h3w2p08yDdU
__________________
-------------------
Dues paid (2017)
RV-14 #140394
Empennage - WIP
Wings - Inventory
YouTube Build Channel
Reply With Quote
  #44  
Old 09-11-2017, 12:29 PM
kiljoy's Avatar
kiljoy kiljoy is offline
 
Join Date: Sep 2014
Location: San Francisco
Posts: 51
Default

So the last week has been interesting. I had taken the week off in hopes of rest and recuperation. Instead it was frantic work and trying to get my head wrapped around the responsibilities of being a flying club maintenance officer.

Anyways, that's all still a mess but there is at least a light at the end of that tunnel. I did manage to get some build time in between work emergencies and plane maintenance work. The ailerons are now doing just fine that I secured some proper drill bits. High speed steel = ****. I mean they're fine for aluminum but stainless steel just laughs at them. I almost had a L vs R mirroring part issue but I managed to avoid that so no ordering of new parts for me!

Here are a few of the vids I put together. There's a few more but those will have to come later. Enjoy:

https://youtu.be/q3WajKiDe0k
https://youtu.be/M0Zg2D9fka8
https://youtu.be/t9xsDNkS5Jc
__________________
-------------------
Dues paid (2017)
RV-14 #140394
Empennage - WIP
Wings - Inventory
YouTube Build Channel
Reply With Quote
  #45  
Old 09-15-2017, 10:55 AM
kiljoy's Avatar
kiljoy kiljoy is offline
 
Join Date: Sep 2014
Location: San Francisco
Posts: 51
Default

I've been continuing work on the ailerons this week. I finally got the correct bits and have made the counterweights succumb to the cobalt! After completing the stiffeners I've finished the left aileron though those videos won't be out until next week.

It's been hard balancing doing my build and my club's maintenance but I believe I've found a good way to strike a balance and have members help out enough to make it sustainable. The best perk is that I get to do any maintenance test flying and bill it to the club

Here are the latest vids:

https://youtu.be/32RHbMpQBb0
https://youtu.be/kN3LM3oszKw
https://youtu.be/lwdpg1SvtVA
__________________
-------------------
Dues paid (2017)
RV-14 #140394
Empennage - WIP
Wings - Inventory
YouTube Build Channel
Reply With Quote
  #46  
Old 09-19-2017, 12:55 PM
kiljoy's Avatar
kiljoy kiljoy is offline
 
Join Date: Sep 2014
Location: San Francisco
Posts: 51
Default Another week.. more deburring

So aileron work continues. Nothing very exciting really. Deburr, deburr, deburr. Here are the next few videos in the series. Enjoy.

https://youtu.be/w-UJhzdb8II
https://youtu.be/-E-e93GKgtE
https://youtu.be/tBlQEgHUOSk
__________________
-------------------
Dues paid (2017)
RV-14 #140394
Empennage - WIP
Wings - Inventory
YouTube Build Channel
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 12:13 PM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.