Another BRS Update for RV10

shoprat

Member
Here is the current update. As last time, email me for current 3D drawings sent with this update if interested.

I?m here to give you an update on the RV10 project evolution.
The schedule was reevaluated due to some structural modifications when the aircraft has A/C installed (very common here in Brazil).

Because of the high loads during the opening of the parachute, some alterations in the design proved to be necessary, and a revaluation of the location on the structure of the aft attachment point was done, causing the delays.

The load reports (Load Determination Report and Load Assessment Report) are been reviewed, with the last draft version of the PIM (Parachute Installation Manual), and the illustrated parts catalogue. The project will be send to final evaluation from BRS by at December 15.

We did our best efforts to minimize the impact on the schedule. The ground extraction tests will be schedule to January/2018.



Bruce McGlamery
[email protected]
 