Default 21iS/U-03 Figure 2

Iím needing clarification. Iím working on the iS fuselage kit. On page 21iS/U-03, Figure 2, at the bottom left side of the diagram, it says ďCS4-4, Both Ends Flush FWD SideĒ. Iím not sure what this means. Does this only apply to the single hole that the arrow appears to be pointing to? And does the flush manufactured head go on the F-01204D-1 side just like the LP4-3 rivets do? I donít understand where the CS4-4 rivet or rivets must go and why it canít be a LP4-3. Thanks
__________________
RV12 - building
Empennage finished
Wings finished
iS Fuselage in progress
ULS Fuselage kit - SOLD


Farmer - corn & soybeans
Firefighter
2018 Dues Paid
Knoxville, IL
Reply With Quote
  #2  
Old 06-05-2018, 09:25 AM
rvbuilder2002 rvbuilder2002 is offline
 
Join Date: Jul 2005
Location: Hubbard Oregon
Posts: 7,714
Default

A CS4-4 rivet is a Counter Sunk / flush rivet.

Because of that, the hole it goes in must be prepared in some way for a flush rivet (dimple countersunk or machine countersunk).

The hole pointed to by the arrow was specified to be machine countersunk in Section 20iS/U, page 3, Step 8, for a CS4-4 countersunk rivet.

The riveting statement means to say the countersunk hole at each end of the bulkhead (it assumes since you are installing a flush rivet, you will be looking for holes that are either dimple countersunk or machine countersunk. At this point in the assemble process there are only two. The upper hole for attachment of the two F-01223 ribs.
__________________
Any opinions expressed in this message are my own and not necessarily those of my employer.

Scott McDaniels
Hubbard, Oregon
RV-6A (aka "Junkyard Special ")
Reply With Quote
  #3  
Old 06-05-2018, 11:06 AM
Rob H Rob H is offline
 
Join Date: Jan 2016
Location: Knoxville, IL
Posts: 91
Default

Okay, that makes sense. I will look for the countersunk rivet hole when I get home. Thanks!
__________________
RV12 - building
Empennage finished
Wings finished
iS Fuselage in progress
ULS Fuselage kit - SOLD


Farmer - corn & soybeans
Firefighter
2018 Dues Paid
Knoxville, IL
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 11:28 PM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.