Default IO 390 Delays

I ordered my engine back in July, with a mid November expected delivery. Got a call from Lycoming in October asking if I would delay delivery. I agreed to a 1 month delay. Called mid December and told to expect a mid January delivery. Called yesterday and told to expect delivery Feb 28. They say that they are having problems with their cylinder vendor. Plan accordingly.
Reply With Quote
  #2  
Old 01-15-2019, 06:40 AM
Cwood2000 Cwood2000 is online now
 
Join Date: Jun 2012
Location: Tallahassee, fl
Posts: 172
Default

Thanks, I was told 6 months on the Thunderbolt, a year ago it was 60 days. Sure delayed my completion date.
__________________
Aka YellaDawg
RV4
RV14 First Flight 10.15.2019
Reply With Quote
  #3  
Old 01-15-2019, 07:11 AM
mturnerb mturnerb is offline
 
Join Date: Apr 2015
Location: Ponte Vedra, FL
Posts: 1,140
Default

I too ordered Thunderbolt last spring and asked Jeff to push delivery until I was ready - it was right on time late August. Makes you wonder what kind of trouble with the cylinder vendor. I'm guessing volume has picked up (especially with IO-390 now being used in production aircraft).
__________________
Turner Billingsley
RV-14A FLYING, N14VB
https://turnerb14a.blogspot.com/
Reply With Quote
  #4  
Old 01-15-2019, 07:13 AM
Tom023 Tom023 is offline
 
Join Date: Jul 2011
Location: Cypress, TX
Posts: 320
Default

Seems to be the norm. Ordered a Thunderbolt at OSH in July 2017 and was told October. Took delivery January 2018 but the delay was actually welcomed. The propeller on the other hand took about six weeks.
__________________
RV14A #140083
Flying! 8/12/19
2019 Donation

Last edited by Tom023 : 01-15-2019 at 07:21 AM.
Reply With Quote
  #5  
Old 01-15-2019, 08:25 AM
kbalch's Avatar
kbalch kbalch is offline
 
Join Date: Jan 2005
Location: Clermont, FL
Posts: 430
Default

Good info. I just ordered my engine and prop last Friday and was told 12 weeks by the girl at Van's. That should work out well, but I hope it doesn't go much longer than that.
__________________
Ken

RV-8 N118KB (#81125) - Sold
RV-14A N114KB (#140494)
Std. kit begun 5/18 - Stick grip wiring, wheel pants, gear leg fairings, and misc. other pre-airport finish-up tasks
Reply With Quote
  #6  
Old 01-15-2019, 10:25 AM
iamtheari iamtheari is offline
 
Join Date: Nov 2017
Location: ND
Posts: 357
Default

Same boat. I ordered after Oshkosh and was told mid-December. I finally was able, with Van's help (thanks to the team at Van's!), to get an answer regarding the cylinder vendor and a current dock date of February 28. I specifically chose Lycoming because the other engine vendors would have had long lead times. Let's hope we all get our IO-390's in time to fly to Oshkosh 2019!
Reply With Quote
  #7  
Old 01-15-2019, 10:36 AM
rvator10 rvator10 is offline
 
Join Date: Apr 2006
Location: Fountain Hills, arizona
Posts: 104
Default

i was told the same by Vans yesterday, my engine is only 2 weeks late today but now estimate is Feb 30th, lets hope that doesn't slip anymore. I'm ready now to hang the engine and finish FWF!.
Reply With Quote
  #8  
Old 01-15-2019, 10:51 AM
Don E Don E is offline
 
Join Date: Aug 2016
Location: West Chester, PA
Posts: 92
Default That could be a very long wait...

Quote:
Originally Posted by rvator10 View Post
i was told the same by Vans yesterday, my engine is only 2 weeks late today but now estimate is Feb 30th, lets hope that doesn't slip anymore. I'm ready now to hang the engine and finish FWF!.
Feb 30? Hmmmm...
Reply With Quote
  #9  
Old 01-15-2019, 11:25 AM
rvator10 rvator10 is offline
 
Join Date: Apr 2006
Location: Fountain Hills, arizona
Posts: 104
Default

28th better?
Reply With Quote
  #10  
Old 01-15-2019, 11:39 AM
mturnerb mturnerb is offline
 
Join Date: Apr 2015
Location: Ponte Vedra, FL
Posts: 1,140
Default

Quote:
Originally Posted by rvator10 View Post
i was told the same by Vans yesterday, my engine is only 2 weeks late today but now estimate is Feb 30th, lets hope that doesn't slip anymore. I'm ready now to hang the engine and finish FWF!.
Being promised February the 30th wouldn't give me a lot of confidence....
__________________
Turner Billingsley
RV-14A FLYING, N14VB
https://turnerb14a.blogspot.com/
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 05:14 PM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.