Working on Section 27 and I think that there is a mistake in the plans.
On 27-04 there is a section of the firewall which is not dimpled for the installation of the battery box. Then on 27-05 there is a section of the top firewall which is no supposed to be dimpled for the battery box. The issue is that 27-04 shows 6 holes to not be dimpled, while on 27-05 there are 7 holes which are not supposed to be dimpled. The battery box bracket only has six holes. So I assume that 27-05 is not correct and that only 6 holes are not supposed to be dimpled.
I want to make sure that I am correct since my next step is to counter sink the corresponding hole in the F-01401D angle bracket. I can always undimple a hole. Kinda hard to uncounter sink a hole.
27-04
27-05
On 27-04 there is a section of the firewall which is not dimpled for the installation of the battery box. Then on 27-05 there is a section of the top firewall which is no supposed to be dimpled for the battery box. The issue is that 27-04 shows 6 holes to not be dimpled, while on 27-05 there are 7 holes which are not supposed to be dimpled. The battery box bracket only has six holes. So I assume that 27-05 is not correct and that only 6 holes are not supposed to be dimpled.
I want to make sure that I am correct since my next step is to counter sink the corresponding hole in the F-01401D angle bracket. I can always undimple a hole. Kinda hard to uncounter sink a hole.